A containerised data centre has a density ceiling because racks, power distribution and cooling all share one fixed volume. Functional separation, the first of Adaptive MDC's five modular design principles, splits the electrical, mechanical and IT components into discrete modules instead. The container's constraint is dimensional, and no internal layout can fix it.
What is the problem with a shared envelope?
An ISO shipping container has a fixed external envelope, with internal dimensions of approximately 2.35 m wide by 2.39 m high. That does not change whatever is installed inside it. A containerised data centre places the IT racks, power distribution and cooling plant in that single volume, so the three systems compete for the same space.
At low rack densities the competition is immaterial, because air-cooling equipment and electrical distribution occupy a modest footprint relative to the space available. However, as density rises, the cooling plant needed to reject heat from the racks and the electrical distribution needed to deliver power to them both grow in proportion to load. The container itself does not grow at all.
Why can't a better internal layout solve it?
Beyond a certain point it cannot, because the constraint is dimensional rather than organisational. Rising density creates the problem, and the fixed envelope prevents it from being resolved. The result is a fixed ceiling on achievable density, built into the geometry rather than a shortfall that more engineering effort would overcome.
What does functional separation change?
In our reference designs, each function sits in its own module. The road transport and handling constraints remain, so transportability is not removed. However, the volume that a containerised design places in one container is spread across a number of modules. The IT white space and its associated distribution can be handled in stacked modules, with different cooling and power configurations accommodated around them.
The effect is to convert the dimensional constraint into a number of independent constraints, each of which can be resolved on its own terms. That makes functional separation a necessary response to rising rack density, not just a convenient one.
What does it look like inside the white space?
Plant such as EPODs (UPS input to output, switchgear and so on), battery rooms and generators have been modularised for years, because each does one job. We can now apply the same principle to the IT white space. That space has cooling above the racks and power distribution at levels well beyond what it was originally designed for, and it still has to leave room for the IT itself and for the large amount of containment that communications cabling for AI services needs. This adds a layer of complexity and services coordination.
Building the modules around those separate functions gives each one the space and coordination it needs, while keeping it accessible and functional. The alternative is one large open data hall.
What makes separated modules work in practice?
Interfaces. The Singapore Aromatics Plant was delivered as 213 modules (Gibb, 1999), and they could be assembled with confidence because the interfaces had been defined and tested on a full three-dimensional model before fabrication began, with engineering, operations and maintenance disciplines all reviewing it. Without that rigour, splitting systems into independent modules risks trading one form of on-site rework for another.
The same applies to a data centre. Separating IT, power and cooling only helps if the interfaces between the modules are defined and tested before anything is built. Our reference designs provide a clear set of interfaces between the IT equipment and the associated power, cooling and communications distribution systems.
How does it connect to the rest of the design?
Functional separation allows cooling and power capacity to be revised without disturbing the structural module, which is the basis of the fourth principle, density agnosticism. It also has a sustainability dimension. Mechanical and electrical plant is estimated to dominate a data centre's embodied emissions (Data Centre Review, 2026), and functional separation moves that plant from site-based construction into factory fabrication.
What should a specifier ask?
- Which systems share a volume, and what happens to that volume as density rises?
- Where are the interfaces between modules, and were they defined and tested before fabrication?
- If cooling or power capacity changes, what else needs to change with it?
The next post looks at standardisation: how to decide what to standardise and what to build conventionally.
Sources
- Data Centre Review (2026) Why Embodied Carbon Must Move Up the Agenda. Available at: datacentrereview.com.
- Gibb, A.G.F. (1999) Off-Site Fabrication: Prefabrication, Pre-Assembly and Modularisation. Whittles Publishing / John Wiley & Sons. Case Studies 4.2.4 (Singapore Aromatics Plant) and 4.3.4 (Fazakerley Prison, Merseyside).
Full references are in the white paper.